CITIZEN CHARTER OF KONKAN RAILWAY
OPENING OF NEW PRIVATE SIDINGS/PRIVATE FREIGHT TERMINALS
CITIZEN CHARTER
1. OPENING OF NEW PRIVATE SIDINGS/PRIVATE FREIGHT TERMINALS** (Greenfield Projects) (When Consultant Engaged) | |||
Sr. No. | Service | Time Limit | Single Window Agency (to be contacted for progress / non-compliance) |
1.1 | In Principle Approval | 35 days | General Manager (Strategic Plg & Business Dev.) gm.spbd@krcl.co.in
|
1.2 | Submit Detailed Project Report (DPR) | 15 days | General Manager (Strategic Plg & Business Dev.) gm.spbd@krcl.co.in
|
1.3 | Detailed Project Report (DPR) Approval | 35 days | General Manager (Strategic Plg & Business Dev.) gm.spbd@krcl.co.in
|
1.4 | Decision on mode of execution of Work | 35 days | Chief Engineer at HQ ce@krcl.co.in
|
1.5 | Preparation time for processing to start work | 60 days | Chief Engineer at HQ ce@krcl.co.in
|
1.6 | Processing of land licensing | 120 days | Chief Engineer at HQ ce@krcl.co.in
|
1.7 | Regional certification after execution of the works | 5 days | General Manager (Strategic Plg & Business Dev.) gm.spbd@krcl.co.in
|
1.8 | Signing of Siding Agreement | 5 days | Chief Commercial Manager ccm@krcl.co.in
|
1.9 | Notification after certification | 5 days | Chief Commercial Manager ccm@krcl.co.in
|
**It is as per Freight Marketing Circular No.11 of 2016 on Pvt.Siding.