Traffic Block between Nagothane and Roha station
Central Railway will take up Traffic block for Commissioning of Nagothane & Roha section Doubling work and Roha yard remodeling work (Pre-NI & NI Work) from 30/03/2017 to 01/04/2017. The following trains will be affected due to this traffic block :-
Duration of Traffic Block:
On 30/03/2017 (Thursday) : 03hrs (12.00hrs to 15.00hrs Traffic Block)
On 31/03/2017 (Friday) : 06hrs (12.35hrs to 18.35hrs Traffic Block for Commissioning of New Panel at Roha station).
06hrs (12.45hrs to 18.45hrs Traffic Block at Nagothane station).
On 01/04/2017 (Saturday) : 02hrs Traffic Block & 01hrs U/Traffic Block
Repercussion on Mail/Express and Passenger Trains :
On 30/03/2017 (Thursday) :
Down Trains:1) 71089 DIVA-ROHA DMU will be short terminated at NGTN (Arr. 11.21hrs)
2) 12218 CDG-KCVL ‘Kerala Sampark Kranti’ Express(JCO-29/03/2017) will be regulated at
KASU from 13.15hrs to 15.00hrs (01’45”) and will be taken over ROHA at 15.35hrs(instead
of 14.10hrs)
3) 16345 LTT-TVC ‘Netravati’ Express will be regulated at PEN from 13.45hrs to 15.00hrs
(01’15”) and will be Taken Over ROHA at 16.25hrs(instead of 14.55hrs).
4) 71095 DIVA-ROHA DMU will be short terminated at NGTN (Arr. 22.06hrs)
Up Trains:
1) 71096 ROHA-DIVA DMU will be run ex NGTN (Dep. 15.57hrs)
2) 22630 TEN-DR Express(JCO-29/03/2017) will be regulated over KR section & Handing
Over ROHA at 15.40hrs & Dadar arrival will be at 19.00hrs(instead of 15.10hrs) (PF-6).
3) 16346 TVC-LTT ‘Netravati’ Express(JCO-29/03/2017) will be regulated over KR section &
Handing Over ROHA at 16.00hrs & further regulated at ROHA for 30minutes (16.00hrs to
16.30hrs) and LTT arrival will be at 19.50hrs(instead of 16.40hrs).
4) 11086 MAO-LTT Double Decker Express (JCO-30/03/2017) will be regulated over KR
Section & Handing Over ROHA at 16.40hrs & further regulated at ROHA for 15minutes
(16.40hrs to 16.55hrs) and LTT arrival will be at 20.15hrs(instead of 17.10hrs)
5) 12224 ERS-LTT Duranto (JCO 29/03/2017) and 22633 TVC-NZM (JCO 29/03/2017)
will be regulated over KR section, if required.
On 31/03/2017 (Friday) :
Cancellation:
1) 50104/50103 Ratnagiri-DR-Ratnagiri Passenger will remain cancelled on 31/03/2017.
Down Trains:
1) 71089 DIVA-ROHA DMU will be short terminated at KASU (Arr. 11.07hrs)
2) 19262 PBR-KCVL Express(JCO-30/03/2017) will be rescheduled ex PBR by 03hrs &
Regulated at KASU from 17.30hrs to 18.05hrs and will be Taken Over ROHA at
18.40hrs(instead of 14.10hrs)
3) 16345 LTT-TVC ‘Netravati’ Express(JCO-31/03/2017) will be rescheduled ex LTT at
14.20hrs(Sch Dep. 11.40hrs) and will be regulated at KASU from 17.15hrs to 18.05hrs and
will be Taken Over ROHA at 19.05hrs(instead of 14.55hrs)
4)12619 LTT-MAQ ‘Matsyagandha’ Express (JCO-31/03/2017) will be regulated at PEN from
17.15hrs to 18.05hrs and will be Taken Over ROHA at 19.30hrs(instead of 18.10hrs)
5) 10111 CSTM-MAO ‘Konkan Kanya’ Express will be leaving CSTM at 23.55hrs (instead of
23.05hrs)
Up Trains:
1) 71092 ROHA-DIVA DMU will be run ex NGTN (Dep.05.33hrs)
2) 71096 ROHA-DIVA DMU will be run ex KASU (Dep.16.10hrs)
3) 16346 TVC-LTT ‘Netravati’ Express(JCO-30/03/2017) will be rescheduled ex TVC by
04hrs(13.50hrs) and Handing Over ROHA at 17.55hrs & further regulated at ROHA for
10minutes (17.55hrs to 18.05hrs) and LTT arrival will be at 21.00hrs(instead of 16.40hrs)
4) 12431 TVC-NZM ‘Rajdhani’ Express (JCO-30/03/2017) will be rescheduled ex TVC by
01hrs late (20.15hrs) and Handing Over ROHA at 18.15hrs & further regulated at ROHA for
15minutes(18.15hrs to 18.30hrs) and Handing Over WRly at 21.30hrs(instead of 19.35hrs).
5) 10104 MAO-CSTM ‘Mandovi’ Express (JCO-31/03/2017) will be Handing over ROHA at
18.50hrs & same will be arrived CSTM at 22.25hrs (instead of 21.40hrs)
6) 22907 MAO-HAPA Express (JCO-31/03/2017) will be Handing Over ROHA at 19.10hrs
and Handing Over WRly at 22.35hrs(instead of 21.15hrs.
6) 50108/50106 MAO-SWV-DIVA Passenger will be rescheduled ex MAO at 08.30hrs
(02’15”) and ex SWV dep. 10.15hrs (01’45”) & will be Handing over ROHA at 21.30hrs &
same will be short terminated at PNVL (Arr. 23.20hrs) i.e 04.20hrs late. The rake will work
as 50120 ex PNVL (Dep.04.45hrs) on 01/04/2017.
On 01/04/2017 (Saturday) :
Cancellation:
1) 50119 DIVA-PNVL Passenger will remain cancelled on 01/04/2017.
Down Trains:
1) 16345 LTT-TVC ‘Netravati’ Express(JCO-01/04/2017) will be regulated at NGTN from
14.10hrs to 14.40hrs and will be Taken Over ROHA at 15.10hrs(instead of 14.55hrs)
2) 19578 HAPA-TEN Express(JCO-31/03/2017) will be regulated at KASU from 14.20hrs to
14.45hrs and will be Taken Over ROHA at 15.35hrs(instead of 15.20hrs).
Up Trains:
1) 16346 TVC-LTT ‘Netravati’ Express(JCO-31/03/2017) will be regulated at ROHA from
13.45hrs to 14.35hrs and LTT arrival will be at 17.40hrs.(instead of 16.40hrs)
2) 11086 MAO-LTT Double Decker Express(JCO-01/04/2017) will be regulated over KR
section & Handing Over ROHA at 14.45hrs LTT arrival will be at 18.15hrs (instead of
17.10hrs)
Passengers are requested to note the changes.